PROCESS AUTOMATION FOR METAL RECOVERY PLANT
The MRP Sequences are split into 3 groups, Group 1 does the crushing of Slag and Stores them into the Surge hoppers, where as the Group 2 and 3 operated together to recover the metal from slag. If any of the field instruments becomes unhealthy in a group, then the entire group sequence will be stopped immediately for safety. Group Sequence Auto Start, Stop are provided in the SCADA System to Start and Stop the Process. If any interlock is not found ok in the group sequence then the process will not carry forward to the next phase. Totalizer concept is implemented to measure how much quantity of Slag is process per day, this can be viewed by the operator in the SCADA screen and can be reset if required.